"When will they arrive?" is usually the second question after the price. The honest answer depends less on the factory than on how quickly artwork is approved. This guide shows a realistic timeline and how to plan around a fixed date such as an open day or a trade fair.
The timeline at a glance
- **Design proof:** usually within six hours on working days after you upload your logo.
- **Corrections and approval:** often the same day; complex designs or several decision-makers can take longer.
- **Production:** 10–12 working days after final approval.
- **Header card packaging:** adds five working days if selected.
- **Shipping:** dispatched with tracking; total delivery is typically 15–17 working days from approval.
Working days exclude Saturdays, Sundays and public holidays.
What happens during production
Our facility in Istanbul has printed custom air fresheners since 2014. After approval the order goes through these steps:
- printing plates are made and both sides are printed in full-colour offset
- the cards are die-cut to the approved shape
- the fragrance is applied in the chosen intensity
- each air freshener is packed individually in airtight film
- a quality check takes place before dispatch
With a capacity of three to four million pieces a month, typical orders from 250 to 10,000 pieces follow the regular timeline. For very large runs we confirm the date with you before you order.
Delivery by destination
Shipping, customs and import charges are included in the price, so there is nothing to pay on delivery. Typical transit times after dispatch:
- Germany, Austria, Switzerland, Benelux and France: a few working days
- UK and Ireland: a few working days, customs handled by us
- Other countries: we confirm the expected date when you order
How to hit a fixed date
Count back from the day you need the air fresheners in hand:
- Event date minus three working days of buffer.
- Minus 15–17 working days for production and delivery.
- Minus one or two days for the design proof and approval.
For an event in five weeks you are comfortable. With three weeks or less, approve the proof quickly and tell us the date in your order notes so we can check it.
Example: planning for a dealership open day
A dealership plans an open day on a Saturday six weeks from now and wants 500 air fresheners with its logo and a QR code to a test-drive booking page.
- Week 1, Monday: logo and QR link uploaded; proof arrives the same afternoon.
- Week 1, Wednesday: marketing and the sales manager approve the proof.
- Weeks 2–3: production (10–12 working days).
- Week 4: dispatch and delivery.
- Weeks 5–6: buffer for handing them out to staff and preparing displays.
The same order placed only three weeks before the event is still possible, but every day of delay in approving the proof now matters.
Reorders are faster to prepare
For a reorder, the artwork, shape and fragrance are already approved. You confirm quantity and any changes, and production can start without a new design round. The production time itself remains 10–12 working days.
What slows an order down
- waiting for internal approval from several people
- missing or low-resolution logo files
- changing the fragrance or quantity after approval
- adding header card packaging late
Frequently asked questions
Can production be faster?
The 10–12 working days include printing, cutting, scenting, drying and packing. If you have an urgent date, contact us before ordering; we will tell you honestly whether it can be met.
When does the clock start?
Production time counts from your final approval of the proof, not from the order date.